Griffin Park already has its new river-viewing deck. Brower Park had both its county and state grants in hand by June 2024, and its renovation is only now scheduled to begin.
On the Shrewsbury River side of Monmouth Beach, money arrives in pieces. Each riverfront project is assembled from separate grants and moves once its last piece lands. That explains why Griffin Park, Brower Park and the two public boat ramps sit at different stages this November, and why the order of the work tracks the funding calendar more closely than any single plan for the river.
The Borough Builds on Grant Money, and the Order Follows
Commissioner Larry Bolsch spelled out the approach in the borough's Fall 2026 newsletter. He wrote that the commissioners expect to carry out many improvement projects "with a very minimal tax increase thanks to our efforts in pursuing several State and County grants." He also noted that the borough's own operations use $.26 of every tax dollar collected.
Paying for parks with grants keeps the borough's share of the tax bill small. It also means a project's schedule depends on award cycles. Here is where each river-side site stood heading into November 2026:
| Site | What is planned or built | Funding named in public records | Status in the Fall 2026 newsletter |
|---|---|---|---|
| Griffin Park | ADA-accessible waterfront pavilion with river-viewing deck; exercise stations on the walking path | Community Development Block Grant; $108,545 county grant in 2025 covering Griffin Park fitness equipment and Memorial Park | Pavilion and exercise stations complete; parking lot paving scheduled for fall |
| Brower Park | Playground, activity area, picnic tables, benches, ADA walkway along the river | $120,000 county grant and $67,000 state grant; project budget estimated at $170,000 in 2024 | Renovations to begin this fall |
| West Street boat ramp | Ramp rebuild | Not specified | Complete and fully operational |
| Tocci Avenue boat ramp | Ramp update plus kayak and paddleboard launch | $100,000 county Municipal Open Space Grant, 2026 | Expected completion in 2027 |
These four sites are in the same stretch of town, but they come from separate funding rounds.
Griffin Park Is the Finished Example
Griffin Park shows what the end of the process looks like. In spring 2026, the borough described a new ADA-compliant gazebo with a river-viewing deck "currently being done to replace the aging building that is currently there," backed by "significant grant funding." By the fall issue, Commissioner Dave Stickle reported the pavilion and deck complete. He also reported new exercise stations along the walking path and security cameras installed to help reduce vandalism. He credited a Community Development Block Grant as "a huge asset" in paying for the work.
Griffin's fitness equipment came from a separate source. In November 2025, the Monmouth County Board of County Commissioners awarded $108,545 to Monmouth Beach for "Memorial Park and Griffin Park Fitness Equipment." So one park drew on at least two programs, and the deck and the exercise stations arrived on their own schedules.
The park's one unfinished item is its parking lot, which is scheduled for paving this fall. The state's municipal public access plan for Monmouth Beach lists Griffin among the spots with open views of the Shrewsbury, along with ballfields, playgrounds, restrooms and parking. The new deck puts that river view at the water's edge.
Dog owners will see a reminder in the same newsletter that Griffin Park "is not designated as a dog park." The note says dogs must be leashed and may be walked around the walking track. Directly below it, the newsletter reprints Ordinance 10-5, which addresses domestic animals in borough parks.
Brower Park Shows How Long the Pieces Take to Arrive
Brower Park sits on the corner of Monmouth Parkway and North Road, and the river borders the park on the water side. Its full name is Priscilla Ireland Brower Park, and the borough also calls it Shorelands Park. It is the clearest example of the grant calendar at work.
Two River Times reported in June 2024 that the borough had won a $67,000 Local Recreation Enhancement Projects grant from the New Jersey Department of Community Affairs for the park. The same article said the borough had already received a $120,000 matching grant from Monmouth County "last year," and it put the estimated total budget at $170,000. Tim Somers, then commissioner of the borough's recreation commission, told the paper the plan was to "replace the tables and benches, which are probably 50 years old at this point," replace the old swing set and extend the walkway.
The county grant came first and the state grant followed in June 2024. The Spring 2026 newsletter said work "will begin this year." The Fall 2026 issue narrowed that to "this Fall." The scheduled start comes more than two years after the state award, and longer still after the county's.
The plan has also grown since 2024. The borough now describes it this way:
- New playground equipment serving children ages 3 to 5, plus an activity area
- New picnic tables and benches
- An ADA-compliant walkway along the river that circles the entire park
- Regrading, new grass, and plantings chosen to reflect the riverside setting
Commissioner Stickle thanked Recreation Committee members Darren Weinstein and Colleen Campbell for helping with the redesign. The loop walkway changes the most about how the park is used. The state access plan already listed a waterfront walkway at Shorelands. The new plan keeps the river edge and adds an accessible path all the way around the park.
The Ramps Come Next, One of Them in 2027
The ramps follow the same pattern. The municipal public access plan names two public boat ramps on the river, one at the end of Tocci Avenue and one at West Street. According to the Fall 2026 newsletter:
- West Street boat ramp: completed and fully operational.
- Tocci Avenue boat ramp: due for an update that adds a kayak and paddleboard launch, expected to be complete in 2027.
The Tocci money is the newest in this story. On September 29, 2026, the county commissioners announced $9.15 million in Municipal Open Space Grants to 27 municipalities. Monmouth Beach's line reads "Griffin Park/Tocci Ave Boat Ramp and Kayak Launch." The borough puts the award at $100,000. The county named Griffin Park and Tocci Avenue together in one line, which suggests the county sees the two as a single stretch of riverfront, from the new deck to the launch. A grant awarded in September 2026 with a 2027 target follows the same timeline Brower did.
The road work running alongside the parks is also grant-funded. The Seaview Avenue paving and drainage project, from Beach Road to Cottage Road, is funded through an NJDOT grant and scheduled to begin this fall.
The River Side Calendar, as the Borough Has Published It
In the order the work appears in public records:
- By June 2024: Brower Park holds a $120,000 Monmouth County grant and a $67,000 state DCA grant, against an estimated $170,000 budget.
- November 2025: The county awards $108,545 covering Griffin Park fitness equipment and Memorial Park.
- Spring through fall 2026: The Griffin Park pavilion, river-viewing deck and exercise stations are built and reported complete. The West Street ramp is reported operational.
- September 29, 2026: The county awards $100,000 for the Tocci Avenue ramp and kayak launch.
- Fall 2026: Brower Park renovations, Griffin Park parking lot paving and Seaview Avenue work are all scheduled to begin.
- 2027: The Tocci Avenue kayak and paddleboard launch is expected to be complete.
The borough posts project updates in its newsletter on monmouthbeach.org.
If you are weighing a home near Griffin Park, Brower Park or one of the river ramps, it helps to know which improvements are finished, which are funded and scheduled, and which are still a year or more away. I follow these projects closely and am glad to talk through any of them with you. BG Realty Services. Let's Connect.